Question 11 The following would be considered external stakeholders: a. Sponsor, department head, project team leader b. Human Resource Manager, Marketing Manager, team member c. Customer, suppliers, public d. Department coordinator, Project Coordinator, Company President

a)
Sponsor, department head, project team leader are part of the organization and are internal stakeholders
b)
Human Resource Manager, Marketing Manager, team member are part of the organization and are internal stakeholders
c)
Customer, suppliers, public are not part of the organization but are external to it and are thus considered under external stakeholders
d)
Department coordinator, Project Coordinator, Company President are part of the organization and are internal stakeholders
So, as per above discussion, option c is the correct option
 
“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”

What Students Are Saying About Us

.......... Customer ID: 12*** | Rating: ⭐⭐⭐⭐⭐
"Honestly, I was afraid to send my paper to you, but splendidwritings.com proved they are a trustworthy service. My essay was done in less than a day, and I received a brilliant piece. I didn’t even believe it was my essay at first 🙂 Great job, thank you!"

.......... Customer ID: 14***| Rating: ⭐⭐⭐⭐⭐
"The company has some nice prices and good content. I ordered a term paper here and got a very good one. I'll keep ordering from this website."

"Order a Custom Paper on Similar Assignment! No Plagiarism! Enjoy 20% Discount"