Borges Machine Shop, Inc., has a 1-year contract for the production of 250,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: Annual contracted units Annual fixed cost Per unit variable cost Equipment (GPE 250,000 $100,000 $15.00 System (FMS) 250,000 S250,000 $14.00 Dedicated Machine (DM) 250,000 $480,000 $13.00 The option GPE is best when the contracted volume is below 150000 units (enter your response as a whole number) The option FMS is best when the contracted volume is between andunits (enter your responses as whole numbers). https://d2vlcm61l7u1fs.cloudfront.net/media%2F694%2F694e8a7a-c347-4da5-b334-c2495e955bfd%2FphpC9kzPf.png

Total cost = Fixed cost + Number of units*Variable cost
GPE = 100,000 + 15*x
FMS = 250,000 + 14*x
DM = 480,000 + 13*x
GPE is best till the point cost is equal to FMS. Hence the point is:
100,000 + 15*x = 250,000 + 14*x
x = 150,000 units
The point up to which FMS is best is from 150,000 till the point the cost becomes equal to DM
250,000 + 14*x = 480,000 + 13*x
x = 230,000
So, the FMS is best from 150,000 to 230,000 units
 
“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”

What Students Are Saying About Us

.......... Customer ID: 12*** | Rating: ⭐⭐⭐⭐⭐
"Honestly, I was afraid to send my paper to you, but splendidwritings.com proved they are a trustworthy service. My essay was done in less than a day, and I received a brilliant piece. I didn’t even believe it was my essay at first 🙂 Great job, thank you!"

.......... Customer ID: 14***| Rating: ⭐⭐⭐⭐⭐
"The company has some nice prices and good content. I ordered a term paper here and got a very good one. I'll keep ordering from this website."

"Order a Custom Paper on Similar Assignment! No Plagiarism! Enjoy 20% Discount"