Part 1 (Textbook Questions) 50 points Data from Chapter Exercise Questions 2 and 3 from CPM 3e Chapter 9 are provided below. Question 2 Activity Immediate Predecessor Duration in days (unconstrained at 8-hours per day) Resource Hourly cost Available Work Hours per Day (constrained) A Evaluate freezers 2 Alcides $45 6 B Chart temperatures 6 Joan $50 4 C Review service record 2 Alcides D Consult with HVAC engineer A,B,C 3 Alcides E Develop construction plan D 10 Joan F Complete IC assignment E 2 Alcides G Complete ROI analysis E 5 Joan H Conduct regulatory review E 4 Joan I Obtain construction approval F,G,H 2 Alcides Question 3 WBS Activity Immediate Predecessor Duration in weeks (unconstrained at 8-hours per day) Resource Hourly cost Available Hours per Week (constrained) 1 Operational definition 1.1 Research literature 3 Becky $35 30 1.2 Identify and define terms 1.1 1 Ann $60 30 1.3 Obtain approval of definition 1.2 2 Clive $50 20 2 Target Selection 2.1 Solicit partners for pilot 2 Ann 2.2 Hold brainstorming meeting 2.1 2 Becky 2.3 Identify characteristics of targets 2.2, 3.1 1 Ann 2.4 Obtain approval of partners 2.3, 1.2, 3.4 1 Clive 3 Question set 3.1 Identify process group members 2 Clive 3.2 Develop question set 2.3 4 Ann 3.3 Prototype and validate question set 3.2 3 Becky 3.4 Add partners 3.1, 2.1 3 Becky 4 Pilot process 4.1 Schedule with target audience 2.4 2 Becky 4.2 Conduct beta test 3.4, 2.4 2 Clive 4.3 Process feedback from target audience 4.2 2 Ann 4.4 Conduct pilot 4.3 2 Clive 4.5 Analyze results 4.4 2 Clive Respond to the following questions: Determine the unconstrained critical path and its length (use days for Question 2, use weeks for question 3; use project days only, no weekends). Determine the total hours and the hours per person required to complete the work? Determine the total labor cost and the labor cost per person? Prepare a Gantt chart illustrating the project length using constrained resource assignments and illustrating logical precedence diagramming for each activity (e.g., show finish-start relationships). Include color-coding by resource for each bar of the Gantt chart. Develop a responsibility histogram for each resource over the length of the project and describe what adjustments, if any, were made to the project schedule to effectively deal with resource overloads or other schedule conflicts related to precedence (logic) requirements Prepare a resourced-constrained (yet resource-leveled) critical path and its length. Prepare a figure similar to Exhibit 9.9 (CPM) illustrating a cumulative cost curve.

Q.2.
Activity Duration ES LS EF LF Total Float Free Float Successor Critical activity
A 2 0 4 2 6 4 4 D
B 6 0 0 6 6 0 0 D Critical
C 2 0 4 2 6 4 4 D
D 3 6 6 9 9 0 0 E Critical
E 10 9 9 19 19 0 0 F,G,H Critical
F 2 19 22 21 24 3 3 I
G 5 19 19 24 24 0 0 I Critical
H 4 19 20 23 24 1 1 I
I 2 24 24 26 26 0 0 Critical
Critical Path – B-D-E-G-I and it takes 26 days.
b. Total hours and the hours per person required to complete the work-
Duration – (2+6+2+3+10+5+2+4+2) * 8 = 288 total hours
Hours of Alcides = (2+2+3+2+2) * 8 = 88 hours required to complete the work
Hours of Joan = (6+10+5+4) * 8 = 200 hours required to complete the work
c. Total labor cost and the labor cost per person
Total labor cost = (88 * 45) + (200 * 50) = $13,960
Labor cost of Alcides = 88 * 45 = $3,960
Labor cost of Joan = 200 * 50 = $10,000
 
“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”

What Students Are Saying About Us

.......... Customer ID: 12*** | Rating: ⭐⭐⭐⭐⭐
"Honestly, I was afraid to send my paper to you, but splendidwritings.com proved they are a trustworthy service. My essay was done in less than a day, and I received a brilliant piece. I didn’t even believe it was my essay at first 🙂 Great job, thank you!"

.......... Customer ID: 14***| Rating: ⭐⭐⭐⭐⭐
"The company has some nice prices and good content. I ordered a term paper here and got a very good one. I'll keep ordering from this website."

"Order a Custom Paper on Similar Assignment! No Plagiarism! Enjoy 20% Discount"