A) The system capacity can be calculated as following ( all numbers are in UNITS/HOUR)
Food Prep = 200
Measure and place in plastic pouch= 175
Prepare Cardboard box = 200
Insert pouch in box= 300
Shrink Wrap box= 200
So it can be clearly seen that 200 units of food are prepared every hour whereas 175 units are measured and placed in a plastic pouch.
So as rest of the processes after 2 are dependent on it the capacity of the system can only be 175 units an hour.
Process 2 /step 2 is the bottleneck as it is the least efficient and rest of the steps depend on it.
B) Slack available is
Null as in step 2 the bottleneck phenomenon occurs
Null as this step itself is the bottleneck
25Units/hour
125 Units/hour
25 Units an hour
C) A capacity of 25Units an hour can be gained by adding capacity to Step 2 which is the bottleneck
D) Factors to keep in mind
Overall efficiency of other machines
Cost of the product hence produced
SWOT analysis of expansion
Quality of the product hence obtained
Difference between theoretical and effective rate and calculation of production.
“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”
What Students Are Saying About Us
.......... Customer ID: 12*** | Rating: ⭐⭐⭐⭐⭐"Honestly, I was afraid to send my paper to you, but splendidwritings.com proved they are a trustworthy service. My essay was done in less than a day, and I received a brilliant piece. I didn’t even believe it was my essay at first 🙂 Great job, thank you!"
.......... Customer ID: 14***| Rating: ⭐⭐⭐⭐⭐
"The company has some nice prices and good content. I ordered a term paper here and got a very good one. I'll keep ordering from this website."