If Annie crashes task A to minimum, the number of days crashed = 8-4 = 4
The crash cost = 27.5
The saving per hour = 40
Thus, actual saving = Saving – Crash cost = 40-27.5 = 12.5
Total saving = Crash days*Actual saving = 4*12.5 = 50$
https://d2vlcm61l7u1fs.cloudfront.net/media%2F44b%2F44b5e247-347f-4090-a1ea-8f7ac90363d3%2FphpklcEa6.png
Path Duration
AB 10
AC 16
ADEF 20
After crashing A, the activities that should be crashed are eith D or E or F. Out of these, the lowest crashing cost is of E.
Hence, E
“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”
What Students Are Saying About Us
.......... Customer ID: 12*** | Rating: ⭐⭐⭐⭐⭐"Honestly, I was afraid to send my paper to you, but splendidwritings.com proved they are a trustworthy service. My essay was done in less than a day, and I received a brilliant piece. I didn’t even believe it was my essay at first 🙂 Great job, thank you!"
.......... Customer ID: 14***| Rating: ⭐⭐⭐⭐⭐
"The company has some nice prices and good content. I ordered a term paper here and got a very good one. I'll keep ordering from this website."