The network precedence diagram as follows :
A
B
C
D
E
F
H
G
I
J
K
The possible paths and their corresponding durations as follows :
A-B-E- K = 8 +3 +7 + 3 = 21
A-B-F-G-J-K = 8 +3 + 8 +3 +6 +3 = 31
A-C-G-J-K = 8 +17 +3 +6 +3 = 37
A-D-H-I-J-K = 8 +5+2+8+6+3 = 32
Since A-C-G-J-K has the longest , duration it forms the critical path
ACTIVITIES ON CRITICAL PATH = A-C-G-J-K
DURATION OF CRITICAL PATH = 37
Slack of activities B.F = Duration of A-C-G-J-K – Duration of A-B-F-G-J-K = 37 – 31 = 6 weeks
All activities lying on critical path have ZERO slack. Therefore, Slack for activity A will be ZERO
SLACK OF ACTIVITIES A AND F ARE ZERO AND 6 WEEKS RESPECTIVELY
“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”
What Students Are Saying About Us
.......... Customer ID: 12*** | Rating: ⭐⭐⭐⭐⭐"Honestly, I was afraid to send my paper to you, but splendidwritings.com proved they are a trustworthy service. My essay was done in less than a day, and I received a brilliant piece. I didn’t even believe it was my essay at first 🙂 Great job, thank you!"
.......... Customer ID: 14***| Rating: ⭐⭐⭐⭐⭐
"The company has some nice prices and good content. I ordered a term paper here and got a very good one. I'll keep ordering from this website."